ATTACHMENT A
Statistical Data And Additional Information
of MADA


A. STATISTICAL DATA






B.GENERAL INFORMATION

MUDA IRRIGATION SCHEME (MUDA I)

Objective


This project was implemented to provide engineering infrastructure suitable for double cropping which incorporated a macro-layout
of irrigation, drainage and farm roads network up to the secondary system.

Design Concept

To utilise as much rainfall and uncontrolled flow as possible since the reservoir by itself could not impound enough water to satisfy irrigation demand. Telemetry network monitoring system was introduced to control the irrigation supply.

Project Cost; Implementation Period

Cost - RM 245 million;
Period - 1965 to 1970

Principle Component

        - Two dams, the Muda and Pedu Dams
          connected by the 7.4 km. Saiong Tunnel
        - Conveyance System
                o Improvement of existing river channel
                o Diversion barrage = 1 no.
                o Bifurcation regulator = 1 no.
                o Regulators = 11 no.
                o Main conveyance canals = 120 km.
        - Internal reticulation system
                o Distribution canals = 1005 km.
                o Drainage channels = 902 km.
                o Farm Road = 803 km
                o Minor Structures = 1,993 no.
                o Pumping Station = 24 no.
        - Coastal Embankment
                o Bund = 100 km.
                o Tidal gates = 25 no.


                                                                      MUDA AND PEDU DAMS


MUDA IRRIGATION SCHEME ( MUDA II )



Objective :
To provide more efficient infrastructure system by introducing tertiary facilities to enable direct access to irrigation, drainage and farm road facilities for optimal farm management. This project covered total area of 26,300 ha., 25% of which constitutes 38 irrigation blocks. Number of farmers benefited from this project is 16,000.

Design concept : Each irrigation block is divided into several Irrigation Service Area (ISA) which are serviced by tertiary systems. Each ISAs are in turn divided into Irrigation Service Unit (ISU) arranged according to irrigation schedule. The block will be irrigated based on 7 days presaturation period by 8 staggered irrigation schedule (subsequently reduced to 6) with canal/drain/farm road density to be increased from 10 m/ha. to 30-35m/ha.
Planning is based on integrated planning and implementation model where farmers as end-user and beneficiary of the system will be involved through a special communication information session called "Kursus Tempatan"



Project Cost ; Implementation Period :
Cost    - RM 185 million :
                                                              Period - 1979 to 1990

Principle Component




MUDA IRRIGATION SCHEME ( MUDA III )


Objective : To provide tertiary irrigation, drainage and farm road facilities to the remaining 67,900 ha. of muda area which still depend on secondary facilities. This project will benefit 34,000 farm families.

Design Concept : It is similar with Muda II Project and Tertiary Development for the "Problem Areas" but the number of ISU and staggered irrigation schedule will be further reduced to 3 along with 10 days presaturation period each in order to syncronise with the total presaturation period of 30 days for the whole Muda area. The top width of the farm road also will be increased from 3.6 m to 4.3 m for better mobility of bigger farm machineries.

Project Cost ; Implementation Period : Cost    - RM 445 million
                                                              Period - 1997 to 2010 (projected)




MUDA IRRIGATION SCHEME
TERTIARY DEVELOPMENT FOR PROBLEM AREA

Objective : This project was an extention to the earlier Muda II Project to cover another 6,450 ha. : 7% consist of 15 irrigation blocks which benefit 2,000 farmers. Total area of 350 ha. was excluded because the land has been developed into commercial tiger prawn farm. Subsequently another 4,630 ha. has been reclassified as "extention project" and included in the Project Muda III, leaving only 1470 ha. actually developed under this project.

Design Concept :
It is similar to the design concept for Muda II Project except the number of ISU and staggered irrigation schedule has been reduced to 4 with 10 days presaturation period for each schedule.

Project Cost ; Implementation Period : Cost    - RM 53 million
                                                              Period - 1991 and still in progress